KYIV, May 14 – Ukraine’s power grid Ukrenergo plans to finish reconstruction of the Berezan 220/3510 kV substation in Mykolaiv region to accept electricity from a solar power plant of Voskhod Solar LLC with the installed capacity of 53.4 MW, the company reported.
"The project provides for the installation of an additional power transformer to ensure the full power output of the solar power plant to the 220 kV network, and oil-filled equipment of the 220 kV switchgear will be replaced with up-to-date efficient and reliable SF6 equipment. Assembly and startup works have been finished on the reconstructed 35 kV and 10 kV switchgears, partially on 220 kV switchgear, as well as DC equipment for own needs," the company said.
|