KYIV, April 4 – As part of preparations for the autumn-winter period of 2023/2024, the operator of the electricity distribution system DTEK Kyiv Grids expects to repair and upgrade 832 power facilities, including 12 high-voltage substations, and 100 km of overhead and cable lines, CEO of the company Denys Bondar has said.
"We must conduct a full audit of our equipment that has come under fire. We must repair the destroyed equipment and create an emergency reserve, which will allow us to successfully go through the next winter, probably no less difficult than the current one. New shelling is possible, new restrictions due to wear and tear of networks that have arisen during this winter period," Bondar said at a press conference in Kyiv on Tuesday.
|