KYIV, July 26 – Coal stocks at warehouses of thermal power plants (TPPs) and combined heat and power plants (CHPPs) are less by 209,700 tons than envisaged in the coal accumulation schedule, the Ministry of Energy has said.
"Over the past ten days, the accumulation of coal at warehouses of thermal power plants has lagged behind the approved schedule. At TPPs and CHPPs, the total actual coal supply is 1.117 million tons, while the planned is 1.326 million tons. That is, the backlog of the schedule is 209,700 tons," the Ministry of Energy said on its website on Friday, July 23.
|