KYIV, June 12 – DTEK will switch units of DTEK Luhanska thermal power plant (TPP, Schastia, Luhansk region) to burning gas or will import anthracite from alternative sources if the Russian Federation continues to delay shipping coal to the TPP, DTEK said on Tuesday.
According to the press release, in the latter case, deliveries will be made by road and to a limited extent.
The company said that the Russian railway since June 2019 has ceased to confirm the shipment of coal for Luhanska TPP due to the non-issuance of quotas for the supply of coal. At present, the stocks in the plant's warehouses amount to 125,000 tons, which is enough for stable operation during 41 days.
|