KIEV, March 14 – Instalaciones Inabensa S.A. (Spain), the contractor for building the 750 kV Zaporizhia nuclear plant-Kakhovska substation power grid, has allowed a delay in the implementation of the four interim stages of the project, Ukrenergo stated.
"The contractor was instructed to provide all the necessary information by March 18. Pivdenna energy system also expects to receive actual data from the company regarding the schedule of delivery of materials, the development of ground and carrying out tests for the strength of steel structures," reads the report.
|