KIEV, Nov. 6 – The Cabinet of Ministers has approved a project construction of the Zakhidno-Krymska-Sevastopol 330 kV power line, including the reconstruction and expansion of two substations, at a combined cost of UAH 1.139 billion.
According to the project, the length of the overland power line will be 96.5 kilometers. The capacity of the Sevastopol and Zakhidno-Krymska substations after their reconstruction will be 200 MVA and 125 MVA respectively.
|