KIEV, May 28 - Energy generating company Donbasenergo (Donetsk) has estimated the construction of two power units with an installed electric capacity of 330 MW each at Sloviansk thermal power plant (TPP) will cost UAH 9 billion, the director for investment projects and capital construction, Ihor Smirnov, has told reporters in Kiev.
According to him, the company has prepared a feasibility study for the construction of the new units, which use high-ash coal combustion technology in their boilers, with circulating fluidized beds.
|